为解决“双高”电网储能选址规划问题,提出包括结构性、运行性两项一级指标及功率波动泰尔熵等6项二级指标的集中式储能选址规划指标体系,建立以熵权法、TOPSIS法为单一评价及模糊Borda法为组合评价的指标体系组合评价模型,获得储能最优选址节点。然后提出基于变分模态分解的混合储能容量配置法,对储能控制功率进行模态分解,根据Hilbert边际谱区分高、低频模态并重构,将高、低频信号能量功率值分别分配给功率型及能量型储能。通过某地区算例结果验证了所提规划策略的有效性。
Abstract:To solve the site selection and capacity planning problem of energy storage in power system with high shares of renewables and power electronics,a centralized energy storage site selection and capacity planning index system including two first-level indexes such as structural and operational indexes and six second-level indexes such as power fluctuation Thiel entropy is proposed,and a combined evaluation model of the index system with the entropy weight method and TOPSIS method as the single evaluation and the fuzzy Borda method as the combined evaluation is established to obtain the optimal location node for energy storage. A hybrid energy storage capacity configuration method based on variational mode decomposition is put forward to perform modal decomposition of energy storage control power,distinguish and reconstruct the high-and low-frequency modes according to the Hilbert marginal spectrum,and allocate high-and low-frequency signal energy power values to the power-and energy-type energy storage. The results of an example in one region verify the effectiveness of the planning strategy.
[1]张子扬,张宁,杜尔顺,等(Zhang Ziyang,Zhang Ning,Du Ershun,et al).双高电力系统频率安全问题评述及其应对措施(Review and countermeasures on frequency security issues of power systems with high shares of renewables and power electronics)[J].中国电机工程学报(Proceedings of the CSEE),2022,42(1):1-24.
[2]孟源,樊小朝,史瑞静,等(Meng Yuan,Fan Xiaochao,Shi Ruijing,et al).基于机会约束及N-1安全约束的风光联合储能系统选址定容优化(Optimization of location and capacity for wind-solar-energy storage combined system based on chance constraints and N-1 security constraints)[J].电网技术(Power System Technology),2021,45(5):1886-1893.
[3]张智,周明,武昭原,等(Zhang Zhi,Zhou Ming,Wu Zhaoyuan,et al).考虑动态频率支撑的储能选址定容规划方法(Energy storage location and capacity planning method considering dynamic frequency support)[J].中国电机工程学报(Proceedings of the CSEE),2023,43(7):2708-2720.
[4]郑重,苗世洪,张松岩,等(Zheng Zhong,Miao Shihong,Zhang Songyan,et al).基于极限学习机的输配一体储能系统选址定容协同优化策略(Collaborative optimization strategy for location and capacity determination of energy storage system considering transmission and distribution integration based on extreme learning machine)[J].电力自动化设备(Electric Power Automation Equipment),2022,42(2):31-40.
[5]吴昊,朱自伟(Wu Hao,Zhu Ziwei).基于熵权-层次分析法综合指标的电网关键线路辨识(Key nodes identification in power grid based on comprehensive index calculated by the entropy weight-analytical hierarchy process)[J].中国电力(Electric Power),2020,53(5):39-47,55.
[6]刘小丽,毛弋,梁杉,等(Liu Xiaoli,Mao Yi,Liang Shan,et al).基于综合介数的电网脆弱线路辨识(Identification of vulnerable lines in power grid based on comprehensive betweenness index)[J].电力系统保护与控制(Power System Protection and Control),2016,44(2):116-121.
[7]刘美君,刘吉龙,李华强,等(Liu Meijun,Liu Jilong,Li Huaqiang,et al).计及电压等级的电网关键节点识别(Critical node identification of power grid considering voltage level)[J].电力自动化设备(Electric Power Automation Equipment),2019,39(3):51-57.
[8]张程,于永军,李华强,等(Zhang Cheng,Yu Yongjun,Li Huaqiang,et al).考量能量裕度及权重因子的电力系统节点综合脆弱性分析(Analysis of nodal comprehensive vulnerability considering energy margin and weight factor for power system)[J].电力自动化设备(Electric Power Automation Equipment),2016,36(3):136-141.
[9]孙玉树,唐西胜,孙晓哲,等(Sun Yushu,Tang Xisheng,Sun Xiaozhe,et al).风电波动平抑的储能容量配置方法研究(Research on energy storage capacity allocation method for smoothing wind power fluctuations)[J].中国电机工程学报(Proceedings of the CSEE),2017,37(增):88-97.
[10]王子琪,张慧媛,许军,等(Wang Ziqi,Zhang Huiyuan,Xu Jun,et al).基于改进人工蜂群算法的区域电网储能系统能量管理优化策略(An energy management optimization strategy for regional power grid energy storage system based on improved artificial bee colony algorithm)[J].中国电力(Electric Power),2022,55(9):16-22,55.
[11]齐晓光,姚福星,朱天曈,等(Qi Xiaoguang,Yao Fuxing,Zhu Tiantong,et al).考虑大规模风电接入的电力系统混合储能容量优化配置(Capacity optimization configuration of hybrid energy storage in power system considering large-scale wind power integration)[J].电力自动化设备(Electric Power Automation Equipment),2021,41(10):11-19.
[12]杨茂,闫琦,苏欣,等(Yang Mao,Yan Qi,Su Xin,et al).季节分型下一种面向风电功率日前预测的深度自适应滤波框架(A depth self-adaptive filtering framework for wind power day-ahead prediction under seasonal classification)[J].南方电网技术(Southern Power System Technology),2023,17(6):62-71.
[13]张晴,李欣然,杨明,等(Zhang Qing,Li Xinran,Yang Ming,et al).净效益最大的平抑风电功率波动的混合储能容量配置方法(Capacity determination of hybrid energy storage system for smoothing wind power fluctuations with maximum net benefit)[J].电工技术学报(Transactions of China Electrotechnical Society),2016,31(14):40-48.
[14]靳保源(Jin Baoyuan).电力系统关键节点及关键线路识别研究(Research on the Recognization of the Critical Nodes and Critical Lines in Power Systems)[D].北京:华北电力大学(Beijing:North China Electric Power University),2019.
[15]吴昊(Wu Hao).计及电网结构和状态的电网关键节点与关键线路的识别研究(Research on the Recognition of Key Nodes and Lines in Power Grid Considering Power Grid Structure and State)[D].南昌:南昌大学(Nanchang:Nanchang University),2021.
[16]谭玉东,李欣然,蔡晔,等(Tan Yudong,Li Xinran,Cai Ye,et al).基于电气距离的复杂电网关键节点识别(Critical node identification for complex power grid based on electrical distance)[J].中国电机工程学报(Proceedings of the CSEE),2014,34(01):146-152.
[17]栗然,靳保源,严敬汝,等(Li Ran,Jin Baoyuan,Yan Jingru,et al).基于改进泰尔熵和熵度的电力系统关键节点识别(Identification of key nodes of power system based on improved Theil entropy and entropy degree)[J].电测与仪表(Electrical Measurement&Instrumentation),2018,55(15):42-46,64.
[18]朱凌志,曲立楠,刘纯,等(Zhu Lingzhi,Qu Linan,Liu Chun,et al).新能源发电集群的改进等效短路比计算方法(Improved calculation method of equivalent shortcircuit ratio for power generation cluster of renewable energy)[J].电力系统自动化(Automation of Electric Power Systems),2021,45(22):74-82.
[19]赵书强,汤善发(Zhao Shuqiang,Tang Shanfa).基于改进层次分析法、CRITIC法与逼近理想解排序法的输电网规划方案综合评价(Influence indicator system for equipment utilization efficiency of active distribution network and its value calculation method)[J].电力自动化设备(Electric Power Automation Equipment),2019,39(3):143-148,162.
[20]侯慧,俞菊芳,谢宇风,等(Hou Hui,Yu Jufang,Xie Yufeng,et al).数据驱动的台风灾害下配网10 kV杆塔受损空间分布预测(Data-driven prediction of spatial distribution of damage to 10 kV towers in distribution network under typhoon disaster)[J].电网技术(Power System Technology),2021,45(9):3681-3692.
[21]李滨,陈姝,韦化(Li Bin,Chen Shu,Wei Hua).风电场储能容量优化的频谱分析方法(Optimization of energy storage capacity based on spectral analysis for wind farm)[J].中国电机工程学报(Proceedings of the CSEE),2015,35(9):2128-2134.
[22] Cartwright M. Fourier Methods for Mathematicians,Scientists and Engineers[M]. London:Ellis Horwood Limited,1990.
[23]于军琪,聂己开,赵安军,等(Yu Junqi,Nie Jikai,Zhao Anjun,et al).基于特征挖掘的ARIMA-GRU短期电力负荷预测(ARIMA-GRU short-term power load forecasting based on feature mining)[J].电力系统及其自动化学报(Proceedings of the CSU-EPSA),2022,34(3):91-99.
基本信息:
DOI:10.19635/j.cnki.csu-epsa.001390
中图分类号:TM715
引用信息:
[1]李滨,谢旭槟,梁振成,等.“双高”电力系统集中式储能选址定容规划策略[J].电力系统及其自动化学报,2024,36(09):31-43.DOI:10.19635/j.cnki.csu-epsa.001390.
基金信息:
国家自然科学基金资助项目(51967001); 广西自然科学基金资助项目(2020GXNSFAA297117)